Wiehle Avenue Pedestrian Overpass at W&OD Trail According to the Fairfax County Department of Transportation (FCDOT), the overpass project is in the Land Acquisition Phase. Here is the anticipated timeline: - Final Design Completion by Summer of 2020
- Right-of-Way Acquisition/Utility Relocation Completion by Spring of 2022
- Land Acquisition Completion by Spring of 2021
- Utility Relocation Completion by Spring of 2022
- Construction Begin by Summer of 2022
- Construction Completion by Summer of 2023
FCDOT received VDOT right-of-way authorization in June 2020 to proceed with land acquisition and utility relocation. Utility relocation involves the relocation of Dominion Energy overhead transmission line (monopole facilities) located on Nova Parks property to accommodate the proposed pedestrian bridge over Wiehle Avenue. For more information contact Shyamali Hauth.
Hunter Mill District Transportation Advisory Council (TAC) Virtual Meeting, July 29 The TAC meeting is scheduled for Wednesday, July 29, 8 to 10 a.m. The meeting is hosted on the Webex platform - use this link to attend and participate in the meeting. You will be prompted to register with your email address and ZIP code before logging into meeting. If you prefer to only listen to the meeting, you may call 1-408-418-9388 and use Access Code:129 749 6752. This is also the number to use if accessing TTY 711. The pedestrian overpass project (above) will be discussed.
The Connector resumed service to Herndon-Monroe Park and Ride bus loop on Monday, July 13. Construction activity continues at the location, including the Kiss and Ride lot, which will be closed until Silver Line Phase 2 service begins next year. Learn more.
|