February 10, 2018

Lake Anne West 2/7/2018
·         Sub-surface flow is expected in low flow conditions until voids are filled
·         Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18
·         Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18
·         TDS punch list items
o   Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rap
o   Cut white pipe back to bank
o   Install pipes under trail at Tributary 1
·         TCOT planting access with gator/cart
·         Tentative schedule for completion by the end of February:
Thursday
2/8/2018
Lower pedestrian bridge (LAW-02) installation
Friday
2/9/2018
Construction entrance removal
Monday
2/12/2018
Upper pedestrian bridge (LAW-02) installation
Thursday
2/15/2018
Paving*
Monday
2/19/2018
Planting
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.