Lake Anne West 2/7/2018
· Sub-surface flow is expected in low flow conditions until voids are filled
· Bridge piers installed for downstream bridge (LAW-02) Tuesday 2/6/18
· Oak tree at tributary 2 made safe with crown removal completed Tuesday 2/6/18
· TDS punch list items
o Stabilize around upstream headwall STA 10+00.00 with A1 Rip Rap
o Cut white pipe back to bank
o Install pipes under trail at Tributary 1
· TCOT planting access with gator/cart
· Tentative schedule for completion by the end of February:
Thursday
|
2/8/2018
|
Lower pedestrian bridge (LAW-02) installation
|
Friday
|
2/9/2018
|
Construction entrance removal
|
Monday
|
2/12/2018
|
Upper pedestrian bridge (LAW-02) installation
|
Thursday
|
2/15/2018
|
Paving*
|
Monday
|
2/19/2018
|
Planting
|
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.