Below are the meeting notes and the updated tentative completion schedule.
TDS crews will not be working next Monday, President’s Day.
20018.04 / Lake Anne West
· WSSI to order and post “No Mowing” signs
· Possible bollard installation discussed to inhibit vehicle traffic
· Tentative schedule for completion by the end of February:
Thursday
|
2/15/2018
|
Lower bridge railings installed
|
Thursday
|
2/15/2018
|
Construction entrance removal
|
Friday
|
2/16/2018
|
Upper bridge footers set
|
Tuesday
|
2/19/2018
|
Upper bridge deck set and railings started
|
Thursday
|
2/22/2018
|
Paving*
|
Thursday
|
2/22/2018
|
Plants arriving
|
*Final asphalt when daytime temps stay above 45° F, towards
end of next week. Paving will be accessed from upstream Bachan Ct.
Let us know if you have any questions.