20018.04 / Lake Anne West
· WSSI to order and post “No Mowing” signs
· Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge
· Tentative schedule for completion by the end of February:
Friday
|
2/23/2018
|
Upper bridge (LAW-01) railings installed
|
Thursday
|
2/22/2018
|
Plants delivered – planting to start next week
|
Monday
|
2/26/2018
|
Paving starts*
|
Wednesday
|
2/28/2018
|
Gravel shoulder installed along path
|
*Final asphalt when daytime temps stay above 45° F and weather is dry, towards
Beginning of next week. Paving will be accessed from upstream at Bachan Ct.