February 22, 2018

20018.04 / Lake Anne West
·         WSSI to order and post “No Mowing” signs
·         Bollard to be installed by TDS to block vehicular traffic at LAW-01 bridge
·         Tentative schedule for completion by the end of February:
Friday
2/23/2018
Upper bridge (LAW-01) railings installed
Thursday
2/22/2018
Plants delivered – planting to start next week
Monday
2/26/2018
Paving starts*
Wednesday
2/28/2018
Gravel shoulder installed along path
*Final asphalt when daytime temps stay above 45° F and weather is dry, towards
Beginning of next week.  Paving will be accessed from upstream at Bachan Ct.