Lake Anne West-
TDS (1 Crew until stream completion and additional crews as needed for bridge and trail paving)
Stream Completion- Week of 2/5
Bridge and Asphalt Trail- 2/12-2/16
Planting- After stream completion 2/12- with the deadline 3/31
Notes:
- I will request permission for paving access from upstream trail entrance (Sunderbriar Cluster). Once we have a better idea of equipment and access we will coordination with Bud and Joe.
- Damaged Verizon Communication Line- Repair underway (complete now). Line was not marked correctly. Unknown resident impact if any.
- Additional measures (prescribed by Chris Fields-Johnson, Davey Institute) will be implemented in March 2018 on Black gum in Tributary 3 and White Oak in Tributary 2. Stream work should be done as soon as practicable to minimize impact.
- Channel alignment may be adjusted in the field to minimize tree impacts.
- Paver path leading to downstream bridge is being assessed by Karen and Charlie for replacement type. Currently the plan is to put back what is currently there.
Let me know if I missed anything or if you have any questions.